Which hoist is the right one? Compare types, numbers and scenarios for the optimal construction site installation.
There are countless types of construction hoists. But which one is right for my site? The Baulift Simulator helps to compare different types, numbers, and scenarios in order to find the optimal installation for the project. Simulate your planned site installation with your schedule, quantities, and personnel requirements — so you always analyse capacities along the real requirements of the construction site.
Using the real quantity and personnel volumes, the optimal number of hoists and types is calculated.
Are the planned capacities sufficient? Or are unnecessary costs incurred? Do we have enough reserves for disruptions?
How long is the average waiting time for personnel during peak times? When can I load material?
A simulation for construction hoists, developed as part of an Innosuisse project. Partners: Amberg Loglay AG, FH Ostschweiz, Postbaulogistik, Alimak and Halter AG.
Use a schedule, ideally from a BIM2LOG workflow.
Configure hoists and construction site parameters. Create various scenarios. Run the simulation.
Make the right decisions based on the simulation results.
In collaboration with FH Ostschweiz, Postbaulogistik, Alimak and Halter AG, simulation models were created that reflect real project conditions.